In this guide
If you live in Rawalpindi or Islamabad and want to send your extra solar units to the grid, you need a connection agreement and a bidirectional (green) meter from IESCO. Most people still call this net metering. For new applicants since February 2026 it is officially net billing, under NEPRA’s Prosumer Regulations 2026. This guide walks through the IESCO application step by step: who can apply, the documents you need, how long it takes, and the mistakes that cause delays.
Net metering or net billing: what applies to you?
Existing net metering users with an agreement signed before 9 February 2026 are reported to keep their old terms until the agreement expires. New applicants come under net billing, where exported units are paid at a fixed buyback rate that is much lower than the tariff you pay for grid units. The application process with IESCO is similar either way. For what changed and how it affects your savings, read Net Billing in Pakistan 2026.
Who can apply?
- An IESCO consumer with a valid connection in their own name, or with the owner’s consent if the meter is in someone else’s name.
- Homes, shops, offices, schools and factories with an on-grid or hybrid solar system.
- The solar system size should match the sanctioned load on your connection. If your system is larger, you may need to apply for a load extension first.
Off-grid systems that never export to the grid do not need a net metering or net billing agreement.
Documents usually required
IESCO can update its checklist, so confirm the latest list at your subdivision office or with your installer. A typical application includes:
- Copy of the applicant’s CNIC
- Copy of the latest paid electricity bill
- Proof of ownership of the property, or the owner’s consent if you are a tenant
- The completed application form for the prosumer connection
- Solar system details: panel, inverter and battery models, system size and a single-line diagram
- Datasheets and certificates for the inverter and panels
- Details of the installer, who should be registered with the Alternative Energy Development Board (AEDB)
Step-by-step IESCO application process
1. Get the system designed and installed by a registered installer
The system must use an inverter suitable for grid connection and be installed safely, with proper earthing, breakers and surge protection. Size it to your daytime use, not just your roof, because exported units now earn a low rate. See our solar system price list for package sizes.
2. Prepare and submit the application
The documents above are compiled into the application and submitted to IESCO, along with the required fees. Your installer usually prepares the technical documents.
3. Technical review and site inspection
IESCO reviews the application and its engineers inspect the site to check the installation, the inverter and the connection point.
4. Demand notice and payment
If the application is approved, IESCO issues a demand notice for the meter and any connection costs. Under the 2026 regulations the prosumer is reported to bear interconnection costs.
5. Agreement and green meter installation
The agreement is signed and IESCO installs a bidirectional (green) meter that records units imported from and exported to the grid.
6. Commissioning and first bill
Once the meter is installed, your system is connected and your bills start showing imported and exported units separately.
How long does it take?
The time depends on how complete your documents are and on the workload at your IESCO office. It typically takes several weeks from submission to green meter installation. Missing documents and a sanctioned load that is too low for the system are the most common reasons for delay.
Common mistakes that cause delays
- Meter in someone else’s name: the owner’s consent or a name change is needed first.
- Sanctioned load too low: apply for a load extension before or with the solar application.
- Unpaid or disputed bills: clear arrears before applying.
- Wrong inverter: an off-grid inverter cannot be used for a grid connection.
- Unclear documents: missing datasheets or a missing single-line diagram send the file back.
Is net metering still worth it in 2026?
Yes, but for a different reason than before. The biggest saving is the grid units you no longer buy, not the units you export. A well-sized on-grid or hybrid system that uses most of its own solar still pays back in a few years. A green meter lets you earn something from the surplus instead of wasting it. For homes with evening use and load shedding, a hybrid system with a lithium battery usually gives the best return.
Frequently asked questions
Can a tenant apply for net metering?
Usually only with the property owner’s written consent, because the connection and the agreement are linked to the meter and the property.
What size system can I connect?
It should generally not exceed your connection’s sanctioned load. A 5kW home system, for example, needs a sanctioned load of at least 5kW. Read our 5kW solar system guide and 10kW solar system guide.
Do I need net metering for a hybrid system?
Only if you want to export surplus units to the grid. A hybrid system works without it, but any surplus beyond what your battery can store will then go unused.
Does Quantum Engineering handle the IESCO process?
Yes. We prepare the technical documents and follow up with IESCO for on-grid and hybrid systems we install. See our installation process.
Get help with your IESCO application
Quantum Engineering designs and installs on-grid and hybrid solar systems in Rawalpindi and Islamabad and handles the net metering paperwork for you. Send your bill for a free design and quote: contact us or WhatsApp +92 336 5564447.
Planning solar in Rawalpindi or Islamabad?
Send us your last 12 electricity bills and get a free system design, quote and payback estimate.